Impact of Coal to Solar & Energy Storage Initiative at the Joppa Plant Site from 2022 – 2025:
~$47 M
Invested at Plant
37 MW
Up to 101 Total Direct, Indirect & Induced Full-Time Jobs Created in the Local Community
Up to $5.9 M in Earrings for Local Workers & $10.2 M Boost for the Local County Economy
Up to 155% Increase In Property Taxes From Plant to Local Goverments
Status Updates and Timeline:
Status: Pre-submission engineering and review
Acres Required for Development: 1.5
Construction Time: 12 – 18 Months
Site Work Begins: Est. Q3 2023
Estimated Delivery Window: June 2025
Estimated New Property Tax Level: $1.7 – $2.1 M