Impact of Coal to Solar & Energy Storage Initiative at the Edwards Plant Site from 2022 – 2025:
~$47 M
Invested at Plant
37 MW
Up to 88 Total Direct, Indirect & Induced Full-Time Jobs Created in the Local Community
Up to $7.1 M in Earrings for Local Workers & $11.7 M Boost for the Local County Economy
Renewed Plant Will Generate More Property Taxes Than Recent Legacy Plant Operations
Status Updates and Timeline:
Status: Pre-submission engineering and review
Acres Required for Development: 1.5
Construction Time: 12 – 18 Months
Site Work Begins: Est. Q3 2023
Estimated Delivery Window: June 2024
Estimated New Property Tax Level: $1.48 – $1.86 M