New power generation needs three things: land, a connection to the grid, and transmission to move the power. Assembling them from scratch takes years. The Kincaid plant site already has the land and the transmission, and an established point of interconnection to build from.
The Kincaid Power Plant has occupied this property in Christian County for decades. The site carries established transmission equipment connecting it to the regional grid, and the plant continues to operate on coal today.
Placing new generation on ground like this reuses infrastructure that already exists instead of building it somewhere else from nothing.
The Kincaid plant site, Christian County, Illinois.
What Is Under Consideration
TechnologySolarUtility-scale solar generation.
Capacity under evaluation20MWSolar capacity being evaluated for the site.
CountyChristianChristian County, Illinois.
Project scope changes as development work proceeds, and no decision to construct has been made. Any project at the Kincaid site would depend on market conditions, permitting, interconnection and other approvals.
What a Project Here Would Mean
Building a project at the Kincaid site would deliver a one-time economic stimulus to Christian County — capital investment at the site, wages for local trades, and spending through the local supply chain.
The figures below are what that was modeled to produce.
Capital investment$63MModeled investment at the plant site.
During construction88Jobs supported in Christian County over the construction period.
Local earnings$6.8MEarnings for local workers during construction.
Local economic output$9.9MAdded economic activity in the county during construction.
Economic impact figures were modeled for Vistra by Dr. David G. Loomis, Strategic Economic Research, LLC.
This Has Been Done Four Times in Illinois So Far
Kincaid is a proposal. The approach and the company behind it are not.
Baldwin68 MW of solar with energy storage in Randolph County, operating since 2024.
Newton52 MW of solar with energy storage in Jasper County, operating.
Coffeen44 MW of solar with energy storage in Montgomery County, operating.
Pulaski405 MW of solar in Pulaski County, complete and generating.
Vistra’s recent investments of more than $1 billion have added 570 MW of generation and 6 MW / 24 MWh of battery storage across Illinois.
Kincaid Site at a Glance
Location199 IL-104, Kincaid, IL 62540
CountyChristian County, Illinois
Coal plant statusOperating on coal
Coal plant retirementYear-end 2027 — September 2020 announcement
Identified opportunityUtility-scale solar
Capacity under evaluation20 MW
InterconnectionExisting plant interconnection and transmission