Impact of Coal to Solar & Energy Storage Initiative at the Coffeen Plant Site from 2022 – 2025:
~$63 M
Invested at Plant
44 MW
6 MW
66 Total Direct, Indirect & Included Full-Time Jobs Created in the Local Community
$5 M in Earnings for Local Workers & 7.3 M Boost for the Local County Economy
Up to 57% Increase In Property Taxes to Local Governments Compared to Land Value
Status Updates and Timeline:
Status: Pre-submission engineering and review
Acres Required for Development: 331
Construction Time: 12 – 18 Months
Site Work Begins: Est. Q3 2022
Estimated Delivery Window: June 2023 – June 2024
Estimated New Property Tax Level: $720 – $900 K
Anticipated Coffeen Development Area:
44 MW of Utility-Scale Solar, 6 MW / 22 MWh Storage