Projected Economic Impact of Coal to Solar & Energy Storage Initiative Development Project at the Newton Plant Site:
~$116 M
Invested at Plant
52 MW
 2 MW
72 Total Direct, Indirect & Induced Full-Time Jobs Created in the Local Community
$5.4 M in Earnings for Local Workers & $7.6 M Boost for the Local County Economy
Up to 12% Increase In Property Taxes to Local Governments Compared to Land Value
Updates:
Community Update:
Status: Pre-submission diligence, engineering and review
Expected Construction Mobilization: Â Winter 2024/2025
Time to Complete: 12 – 18 months
Estimated Commercial Operations Date: TBD
Updates:
Community Update Presentation: Review our latest community update
Status: Pre-submission diligence, engineering and review
Expected Construction Mobilization: Â 2023
Time to Complete: 12 – 18 months
Estimated Commercial Operations Date: Fall 2024